There are two key factors that’ll thrust your project into the throes of success: good communication and good planning.
The first is accomplished by building a great report with your team through open channels of honesty, humility, and encouragement.
The second is brought on by organizational skills, team engagement, and foresight. While I’ve already gone into great detail in many of my other project management guides, I want to focus on planning. Particularly, one fundamental tool in your project planning arsenal: PERT charts.
PERT (program evaluation and review technique) charts are a graphical representation of a project’s timeline, tasks, and the dependencies between those tasks.
These charts are used as a project planning tool for the purposes of establishing the amount of time it will take to complete your project, planning out who is responsible for each task, and aiding in finding a critical path.
This is a fair question since there are a fair amount of structural similarities between Gantt charts and PERT charts. Both Gantt charts and PERT charts display project tasks, show task dependencies, and help you identify your critical path.
In terms of visual differences, PERT charts are laid out as a network diagram that displays the order of tasks, while Gantt charts are shown as a horizontal bar graph. However, the biggest difference between the two is when they are used.
I’ve laid out a Gantt chart and PERT chart example comparison so you can understand the differences:
PERT network charts are used during the planning phase of your project to map out your project and understand the process for completion, typically as part of a feasibility study.
A PERT chart will show how long it will take to deliver a project down to the individual task completion times, which tasks are connected to which, and who is responsible for those tasks. These charts are an essential ingredient for nailing down your project scope.
On the other hand, Gantt charts are used during the execution phase of the project management process.
These charts, used in conjunction with burndown charts, will lay out your project on a calendar timeline and show you exactly where you are along the process. Gantt charts are meant to be a task management tool rather than a project planner.
However, if your project management software lacks any PERT functionality, which many of them do, you can substitute a Gantt chart for your project planning.
If I’m being honest, you should always use a PERT chart or some other form of an organizational tool when planning out your projects.
That being said, there are times when you can get away with not using a PERT chart, like smaller personal projects that only require checklists.
However, there are two key instances when a PERT diagram is crucial for mapping out the way forward:
PERT charts help make sense of the chaos when planning out complex projects. These are the projects that have multiple tasks in progress at one time that require specific completion windows and lots of different parties necessary to finish them. A PERT chart will help you understand which tasks are dependent on others and the order you must complete them.
As I mentioned before, a PERT chart is typically employed as one of the potential tools in your feasibility study arsenal. This diagram is used not only as a visual structure for how your project is conducted but also as a guide for how long the project will take.
Since time is one of the core aspects of project feasibility, a PERT chart is the perfect tool for helping you determine whether your team can overcome this obstacle.
Since your project almost certainly will benefit from the use of one of these diagrams, I’ve laid out six steps for successfully creating a PERT chart.
You’ll find the steps in this process are very similar to identifying your critical path, which is extremely helpful since these diagrams are one method for mapping out that path. More on that later.
Milestones, or deliverables, are kind of like the checkpoints in a racing video game, and every turn, pass, or straightaway you drive are the tasks you perform to complete those checkpoints.
In order to create a PERT chart, you have to know all of the major milestones your team will have to accomplish and the tasks that’ll make that happen. List out these milestones and their individual tasks.
You’ve listed all of your milestones and tasks necessary to complete your project, so now it’s time to put those tasks into the correct sequence for completion.
While establishing this sequence and order of tasks, be sure to point out any task dependencies.
This is the most technical step of the PERT diagram creation process. If you’re already familiar with the critical path method, you’ll know there are three specific time criteria you have to figure out for each task:
Once you’ve determined all three of these criteria and listed out the sequence of your tasks, you’re ready to create your PERT chart.
You can create a PERT chart either by drawing one up yourself or by generating one using PERT software. The visual construction of a PERT chart isn’t tied just to the examples used above. PERT is more of a function, rather than a visual style of representing a project structure.
Create your PERT chart in whatever way makes the most sense to you, but just be sure to include all of the information you gathered in the previous steps in order to construct it.
Now that you’ve created your PERT chart with all of the relevant information, you can use this chart to identify the critical path of your project. Your critical path is the identification of the most important steps necessary that’ll help you determine the minimal duration of your project.
As an example, I created a PERT chart for my critical path method guide that maps out the critical path for grilling a steak:
In this PERT chart, I’ve used the earliest start time (EST), earliest finish time (EFT), and the time to complete (TTC) to identify the shortest possible finish time and draw out this critical path in red.
If I were to follow this basic critical path, I would have everything I needed to prepare and cook a steak successfully.
Your PERT chart is a planning tool that is not set in stone. This diagram can be changed whenever circumstances are altered during the project execution phase.
Use your PERT chart as your initial roadmap for your project and transition over to a Gantt chart for the purposes of oversight and management.
It’s very rare for project management platforms to offer any sort of PERT functionality. As far as I’ve seen, all of the project management software options that I’ve reviewed haven’t included this feature and instead opt for users to use Gantt charts for their planning instead.
Don’t worry though; all is not lost. If you’re set on developing PERT charts using your computer, there are plenty of PERT chart generators out there for you to choose from. Here are some of the best PERT chart software options on the market today.
SmartDraw is a cloud-based chart generation software that’ll work on both your desktop, Mac or PC, as well as your mobile phone, IOS and Android. This tool already includes several PERT chart templates that you can use to create the perfect diagram for your project.
All you have to do is select a template and input your project data to create your PERT chart complete with all different kinds of symbols, numbers, and task flows.
Lucidchart is a desktop-based chart creation software that seems to function more like Microsoft Paint than anything else. Luckily this makes it a very easy app to pick up and run with. All you have to do is click and adjust the shapes in your chart, add your information, and off you go.
What’s more, Lucidchart will integrate with some of the most popular office suite and project management software options on the market, such as GSuite, Microsoft Office, Jira, Slack, and many others.
Last, but not least, we have Creately. This platform uses a simple drag-and-drop system for creating all kinds of organizational charts, including PERT diagrams. This tool combines many of the positive aspects of the last two options.
When it comes to multi-platform use, Creately is available on Mac, Windows, Linux, IOS, and Android. As for integrations, it’ll sync with all kinds of other tools like Slack, GSuite, Jira, and Microsoft OneDrive.
If you’ve stumbled on this piece about PERT charts, then chances are you know quite a lot about project management and you’re moving into the more advanced aspects of planning and execution.
Luckily, we have lots to offer you here at The Ascent, from project management principles guides to best practices lists. Be sure to check out everything we have to offer for project managers of all experience levels.
Our Small Business Expert
We're firm believers in the Golden Rule, which is why editorial opinions are ours alone and have not been previously reviewed, approved, or endorsed by included advertisers. The Ascent does not cover all offers on the market. Editorial content from The Ascent is separate from The Motley Fool editorial content and is created by a different analyst team.